The dish rarely fails outdoors — what fails is the equipment behind it, taken out by a surge that rode in on the antenna cable. Get the electrical side right and the install holds.
How we approach the electrical side
Assess the mast
Check whether the mounting mast is conductive and how it sits relative to the roofline and any existing lightning protection system.
Bond to earth
Where a conductive mast rises above the roofline, bond it to the building's earthing system per common EU practice.
Fit SPDs
Install surge protective devices on the data line entry and on the power feed to the router or antenna supply.
Finish the entry
Route a drip loop, seal the cable entry point and add strain relief so the connection stays weatherproof and mechanically sound.
What actually protects the equipment
Line and power, both
An SPD on the data line alone leaves the power feed as an open path — protect both.
Induced, not direct
Most damage comes from induced surges from nearby strikes traveling in on the antenna cable, not a direct hit on the dish.
Bonding, not isolation
A conductive mast left unbonded above the roofline is a lightning rod with no planned path for the energy to go.
Inside the protected zone
Where the building already has a lightning protection system, mount the antenna inside its protected zone rather than above it.
Both entry points
A data-line SPD and a power-feed SPD close different paths into the router — one without the other is half the job.
Weatherproof by design
Drip loop, sealed cable entry and strain relief keep water ingress and cable fatigue from undoing the electrical work.
What we stock for this job
Components for the earthing and surge-protection side of a rooftop antenna install, ready to ship.
- Surge protective devices (data + power)
- Earthing and bonding conductors
- Weatherproof enclosures
- Cable glands and entry seals
- Technical guidance from our engineers
Frequently asked questions
Does a Starlink dish need a direct lightning strike to cause damage?
No — most equipment damage comes from induced surges carried in on the antenna cable from a nearby strike, not a direct hit on the dish itself.
Does the mast really need to be bonded to the building's earthing system?
A conductive mast that rises above the roofline should be bonded to the building earthing system, following common EU practice — your electrician confirms the exact method for the site.
Where should the SPD go — on the cable or on the power supply?
Both. Fit one on the data line where it enters the building and another on the power feed to the router or antenna supply.
What if the building already has a lightning protection system?
Mount the antenna inside the protected zone of the existing system rather than above it, so it isn't the highest point exposed to a direct strike.
Is this guidance enough to sign off the install?
No — this page is engineering guidance. Local electrical code and a qualified electrician determine the final design and sign-off for the site.