Insulation resistance · Loop impedance · Zs · BS 7671 · KNX cable · 10 min read

Insulation Resistance and Loop Impedance Testing for Installation Commissioning

Insulation resistance and loop impedance measurements are the two most critical commissioning tests for any new electrical installation. Together they prove that the cable insulation is sound and that protection devices will operate fast enough to prevent electric shock injury under earth fault conditions.

Purpose and applicable standards

BS 7671 Section 643 and IEC 60364-6 clause 6.3 mandate both insulation resistance and loop impedance testing as part of initial verification for every new electrical installation. These tests must be completed before the installation is energised for normal use and before any Electrical Installation Certificate is issued.

TestStandard clausePurposeInstrument
Insulation resistance (IR)BS 7671 S643 / IEC 60364-6 cl.6.3.3Verify cable insulation integrity — no breakdown or moisture ingressMegger MIT400, Fluke 1587FC
Earth continuityBS 7671 S643 / IEC 60364-6 cl.6.3.2Verify PE conductor connected throughout — no open circuitsLow-resistance ohmmeter (mΩ)
Loop impedance (Zs)BS 7671 S643 / IEC 60364-6 cl.6.3.4Verify fault clearance time within 0.4s — MCB will trip fast enoughFluke 1662, Megger MFT1741
Prospective fault current (PSCC)BS 7671 S434 / IEC 60364-4-43Verify SCPD breaking capacity ≥ available fault current at incomerFluke 1662 PFC function

Insulation resistance test instrument and minimum values

The insulation resistance (IR) test applies a high DC voltage to the cable and measures the resulting leakage current through the insulation. Good insulation allows only an extremely small current — measured in megaohms of resistance. Damaged, wet, or contaminated insulation shows lower resistance.

IR test voltages and minimum values (BS 7671 Table 64)

Circuit nominal voltage    Test voltage (DC)    Min IR (MΩ)
SELV / PELV (≤ 50V AC)    250V DC              ≥ 0.5 MΩ
230/400V (standard)        500V DC              ≥ 1 MΩ
Above 400V                 1000V DC             ≥ 1 MΩ

Test duration: 1 minute (steady-state reading)
The reading should stabilise — a rising reading over
60 seconds indicates good insulation (polarisation effect).
A falling or fluctuating reading indicates moisture or fault.

Practical interpretation:
  New installation, good cable: ≥ 100 MΩ (often 1000+ MΩ)
  Acceptable minimum (BS 7671): ≥ 1 MΩ
  Investigate if: < 10 MΩ — possible cable damage or damp
  Fail (mandatory investigation): < 1 MΩ

Temperature effect: IR halves for every 10°C rise in cable
temperature. Test at ambient temperature and record
temperature — adjust if comparison needed with future tests.

IR test procedure for KNX panel circuits

KNX panel circuits include both standard 230V final circuits and low-voltage KNX bus circuits. Each requires different test voltage and different preparation. Applying the wrong test voltage to KNX devices will cause permanent damage.

Step-by-step IR test for 230V circuits in KNX panels

Step 1: Open all MCBs and RCBOs in the panel
Step 2: Remove all plugs from socket outlets
Step 3: Disconnect all sensitive electronic loads:
  - KNX PS640 power supply (remove from DIN rail or
    disconnect bus cable connections)
  - All KNX actuators with 230V outputs
    (disconnect load cables, not KNX bus connections)
  - LED drivers, DALI power supplies
  - Any device with semiconductor input filtering
  - Variable speed drives, UPS modules
Step 4: Short L and N together at the origin
  (use a shorting test lead with crocodile clips)
Step 5: Connect Megger MIT400 or Fluke 1587FC:
  Test lead A → L+N shorted terminal
  Test lead B → PE (earth) terminal
Step 6: Set instrument to 500V DC
Step 7: Apply test for 60 seconds — read IR at 60s
Step 8: Record IR (MΩ), date, time, ambient temperature
Step 9: Discharge cable (instrument auto-discharges) before
  touching conductors — allow 1 second per 1 MΩ of IR

Fault isolation if IR < 1 MΩ:
  Disconnect each cable at panel end, retest each section
  Progressively isolate until faulty section identified
  Inspect for: damaged cable sheath, wet conduit, crushed cable

Never apply 500V DC to KNX bus cables or devices: KNX TP bus cable is rated to 120V DC maximum. KNX devices have input capacitors and transient suppressors that will be destroyed by 500V DC. Always disconnect and isolate all KNX equipment before applying 500V IR test voltage, and use the separate 100V DC procedure for the KNX bus cable itself.

IR testing of KNX TP bus cable

The KNX TP bus cable (YCYM 2×2×0.8mm²) is SELV-rated and requires a lower test voltage than mains wiring. The bus cable insulation must still be verified — particularly on long cable runs where mechanical damage from other trades is possible.

KNX TP bus cable IR test procedure

KNX cable specification: YCYM 2×2×0.8mm²
  Insulation rated to: 50V AC, 120V DC
  Test voltage: 100V DC (do NOT use 250V or 500V)

Disconnect ALL KNX devices before testing:
  Unplug every KNX device from bus terminals
  Remove KNX PS640 or disconnect bus terminals
  Bus cable under test should be fully isolated at both ends

Test points (three measurements per cable run):
  1. KNX+ to KNX− (pair-to-pair)
  2. KNX+ to screen/drain wire
  3. KNX− to screen/drain wire

Minimum IR: ≥ 1 MΩ for cable run up to 100m
  (shorter runs should show proportionally higher IR)

Fail indicators — possible causes:
  < 1 MΩ between conductors:
    Moisture in a termination sleeve or junction box
    Pinched or crushed cable jacket in cable tray
    Incorrect cable (non-screened) used on part of run
  < 0.5 MΩ to screen:
    Screen grounded at multiple points (ground loop)
    Screen insulation damaged, cable sheath cut

KNX screen grounding rule (for EMC):
  Ground screen at ONE point only (typically at panel)
  Other end: screen floating or connected via 100nF capacitor
  Verify screen grounding before IR testing — a shorted
  screen-to-ground at both ends appears as a fault

Earth continuity testing

Earth continuity testing verifies that the protective earth (PE) conductor provides a continuous low-resistance path from every exposed conductive part back to the main earth bar. A broken or high-resistance PE conductor leaves exposed metalwork energised during a fault until the overcurrent device eventually trips.

Earth continuity test procedure

Instrument: low-resistance ohmmeter
  Examples: Megger DLRO10, Ductor tester, or the continuity
  function of Fluke 1662 / Megger MFT1741 (limited to mΩ)
  Test current: ≥ 200mA (to overcome surface oxide films)

Test points:
  Each metal enclosure → main earth bar (MEB)
  Each cable gland (metal) → MEB
  Each exposed conductive part → MEB
  Each DIN rail → MEB (via earthing clip)

Maximum resistance (BS 7671 and IEC 60364):
  Main protective bonding conductors: ≤ 1 Ω
  Final circuit PE conductors (to furthest point): ≤ 1 Ω

KNX DIN rail enclosures — specific check:
  DIN rail must be PE bonded (earthing clip or copper braid)
  Test: DIN rail surface → PE terminal block
  Target: < 0.5 Ω
  Many DIN rail mounting problems are found here — springs
  and paint prevent good contact without dedicated earthing clips

Test result format:
  Location → MEB resistance (Ω) → PASS/FAIL

Loop impedance test (Zs)

Earth fault loop impedance (Zs) is the total impedance of the fault current path: source → line conductor → fault point → PE conductor → source. Low Zs enables the overcurrent device to trip within the 0.4 second limit required for final circuits serving socket outlets (TN systems).

Maximum Zs values for MCB disconnection (BS 7671 Table 41.1)

MCB type / rating    Max Zs (Ω) for 0.4s disconnection
Type B, 6A           9.58 Ω
Type B, 10A          5.74 Ω
Type B, 16A          2.87 Ω
Type B, 20A          2.30 Ω
Type B, 32A          1.44 Ω
Type C, 6A           4.79 Ω
Type C, 10A          2.87 Ω
Type C, 16A          1.44 Ω
Type C, 20A          1.15 Ω
Type C, 32A          0.72 Ω
Type D, 16A          0.72 Ω
Type D, 32A          0.36 Ω

Test procedure:
  Use no-trip (LoΩ) mode — 15ms current pulse, avoids
  tripping RCDs during measurement
  Instruments: Fluke 1662, Megger MFT1741 in LoΩ mode
  Measure at furthest point of each circuit (socket, actuator)
  Record measured Zs × 1.20 temperature correction factor
  Compare corrected Zs against table above

If Zs > maximum permitted:
  Increase PE conductor cross-section (reduce resistance)
  Add supplementary bonding at the load end
  Reduce circuit length (add sub-distribution board closer)

Loop impedance for KNX actuator circuits

KNX switch actuators (such as MDT AKD-0824V 8×16A or Schneider MTN6730-0001) act as intermediate connection points between the panel MCB and the final loads. Loop impedance must be measured at the actuator output terminals — not just at the panel — since this is where the 230V load connects and where a fault is most likely.

Measuring Zs at actuator outputs

For multi-channel switch actuators in sub-distribution boxes remote from the main panel: test Zs at each 230V output terminal of the actuator. This includes the cable resistance from panel to actuator plus actuator terminal resistance.

For long cable runs (over 50m from panel to actuator): calculate expected Zs before site test. If calculated Zs approaches the maximum limit, upsize PE conductor to 2.5mm² or 4mm² regardless of MCB size.

Actuator PE connection verification

Some KNX actuators have a metal housing that must be PE bonded via the DIN rail earthing clip. Verify: actuator housing → DIN rail → panel PE bar, resistance less than 1Ω.

Also verify: PE terminal block at actuator output (load wiring) is connected to the panel PE bar, not floating. A common wiring error is connecting PE only at the panel and not running a green-yellow PE conductor to the actuator output terminal block.

Prospective fault current at incomer

The prospective short-circuit current (PSCC) at the panel incomer determines what breaking capacity the incomer SCPD must have. This must be measured on site — network PSCC varies by location and network topology, and cannot be assumed from nominal supply data alone.

PSCC measurement at panel incomer

Instrument: Fluke 1662 (PFC function), Megger MFT1741 (PFC)
  Measures prospective fault current using loop impedance
  method — safe, non-destructive

Connection: at panel incomer terminals (before MCB)
  Requires supply to be live — coordinate with client
  Use appropriate PPE: insulated gloves, face shield

Measurements required:
  Line-to-neutral PSCC (L-N): e.g. 3.2 kA
  Line-to-line PSCC (L-L): e.g. 5.5 kA
  Use the HIGHER value (L-L is typically higher) as worst case

Actions based on result:
  PSCC ≤ MCB breaking capacity → no action required
  PSCC > MCB breaking capacity → options:
    Upgrade MCB to higher breaking capacity (B-class → H-class)
    Install HRC fuse upstream to limit fault energy
    Install MCCB with adequate breaking capacity (10–50 kA)

Record on Schedule of Test Results:
  Measured PSCC (kA) at incomer
  SCPD type and rated breaking capacity
  Result: SCPD adequate PASS / FAIL

Schedule of Test Results documentation

The Schedule of Test Results is the legal document that records all commissioning test results. It forms part of the Electrical Installation Certificate (EIC) for new installations or the Electrical Installation Condition Report (EICR) for periodic inspection. Both BS 7671 and IEC 60364-6 Annex C define the required format.

Schedule of Test Results — required fields

Distribution board section:
  Board reference, location, supply voltage/frequency
  Earthing arrangement: TN-C-S / TN-S / TT / IT
  PSCC at origin (kA)
  Earthing conductor size (mm²)
  Main bonding conductor sizes (mm²)

Per circuit (one row per circuit):
  Circuit reference and description (e.g. "L1 — KNX Lighting West")
  Number of points (sockets, luminaires, actuator outputs)
  Circuit type: radial / ring / spur
  Conductor cross-section: line / neutral / PE (mm²)
  Max Zs permitted (Ω) — from Table 41.1
  Earth continuity resistance (Ω)
  Insulation resistance (MΩ) between: L+N → PE
  Polarity: correct (C) / incorrect (I)
  Measured Zs (Ω) at furthest point
  RCD rated residual current I△n (mA)
  RCD measured trip time at I△n (ms)
  MCB / RCBO rating (A) and type (B/C/D)
  Overall result: PASS / FAIL

Signatures required:
  Inspection and testing engineer (name, signature, date)
  Responsible person (company, registration number)

Retention: minimum 10 years commercial, life-of-installation residential
Copies to: building owner, local authority (if required), insurer

Need installation test documentation for sign-off?

We provide complete Schedule of Test Results including insulation resistance, loop impedance Zs, RCD testing and PSCC measurement — all in BS 7671 and IEC 60364-6 format for building control and insurer sign-off.

Request a quote →
Loading...
Back to top